Bringing pace and simplicity to challenging macro site work
The Port of Tilbury is the principal port of London, handling the importation of paper, cars and many other bulk cargoes. It also hosts the London International Cruise Terminal, one of the UK’s most historic passenger ports, dubbed “the quay to the capital”. In locations like this, connecting hundreds of thousands of people to their mobiles at once is commonplace. So when an outdoor site needs upgrading (to 5G like this one) or moving as part of the broader network plans, it must be done quickly and with no connectivity interference for customers.
Project type
3 weeks
Three weeks from nomination to agreed design
2 months
Two months to planning permission, using emergency route
3 months
Passive build work was underway within three months
Using property know-how for pace
In less than six months we completed the design and passive installation process, readying the 30 metre ground mast site for the 5G equipment upgrade VMO2 had planned.
Masts
Mobile masts or towers can be built on the ground as well as on rooftops (and can even be temporary). They’re very carefully located so that they provide the maximum possible coverage for the mobile network operator’s customers.

Read our next case study

Find out more about
Omni 4G/5G

Find out more about
Freshwave
Understand your building’s connectivity
Book a signal survey to see how indoor connectivity could be improved across your building.